Lift modernisation Le Marais

20th August 2015

The modernisation works to the even lifts in blocks E & F Le Marais will start Monday 12th October 2015 and will be completed by Friday 11th December 2015. The odd lift in the blocks will be  modernised in the first half of 2016 to avoid inconvenience to residents and visitors over the Christmas period. 

The work will be carried out by OTIS who have a good reputation in the island and have been made aware of the importance of delivering this project within the above dates. 

We are mindful that some people may have difficulty using the stairs for a prolonged period of time. If you have concerns about this please contact us as soon as possible to enable us to suitably assist you and efficiently meet your needs. Once the lifts have been fully modernised the reliability will be greatly increased.